What Is STP in MEP? Sizing and Design Guide for Consultants

STP | For MEP Consultants

What Is an STP in MEP? A Practical Guide for Consultants, Architects and Builders

Where the STP sits in MEP and plumbing design, the inputs you need to size it, space and installation choices, coordination with civil and electrical, and the design-stage mistakes that cost the most.

By Brivith Engineering12 min readUpdated November 2026
Where the STP sits in MEP and plumbing design Cross-section of a residential tower showing soil stacks draining to a basement STP, treated water pumped to a terrace flushing tank through dual plumbing, landscape irrigation, odour exhaust, panel on DG backup and sludge tanker access. BASEMENT FLUSH TANK Screen Equalise Bio reactor Settle Filter + UV Treated water 1 2 3 4 5 6 7 Where the STP sits in MEP design 1Soil and waste stacks carry sewage down (Plumbing) 2STP chambers in the basement (Plumbing + Civil) 3MCC / PLC panel on DG backup (Electrical) 4Odour exhaust for enclosed STPs (Mechanical) 5Treated water riser to flushing (dual plumbing) 6Landscape irrigation from treated water 7Sludge tanker access at ground level (Civil) Raw sewage Treated water Sludge Exhaust air Illustrative only, not to scale. Brivith Engineering
Figure 1. Where the STP sits in MEP and plumbing design: drainage in, treated water out for flushing and landscaping. Illustrative, not to scale.

An STP in MEP is the sewage treatment plant that a building’s plumbing design collects, sizes and coordinates. It receives the building’s sewage, treats it biologically and sends the treated water back for flushing, landscaping or cooling tower make-up. For MEP consultants, architects and builders, the STP is not a vendor item to drop in at the end. Instead, it shapes basement levels, power load, ventilation and the dual plumbing network from the concept stage.

This guide answers the questions consultants actually ask: what an STP in MEP covers, how to calculate STP size, where to place it and which design-stage mistakes cost the most.

Quick answer

In MEP design, the STP is the end point of the drainage system and the start of the recycled water system. Size it from population × water demand × about 80% sewage return, fix its location before structural drawings freeze, and coordinate civil, electrical and ventilation inputs early.

135 lpcdNBC and CPHEEO water demand benchmark for residences with full flushing
80%Share of water supply CPHEEO expects to reach the sewers
3.0CPHEEO peak factor for a contributory population up to 20,000
20,000 m²Built-up area above which building projects generally need prior Environmental Clearance

Norms are referenced for design guidance. Confirm current city bye-laws, SEIAA conditions and MPCB consent requirements for each project.

What is STP in MEP?

STP in MEP means the sewage treatment plant designed as part of a building’s plumbing and public health engineering (PHE) scope. MEP stands for mechanical, electrical and plumbing. The STP belongs mainly to the “P”, because it receives soil and waste water from the drainage network. However, it also draws power from the electrical design and needs air from the mechanical design.

In practice, the MEP consultant defines the STP capacity, inlet and outlet points, reuse plan and space allowance. The specialist STP vendor then designs the process, equipment and controls. Consequently, the quality of the consultant’s brief decides how well the plant performs for years after handover.

DisciplineWhat it owns for the STP
Plumbing / PHECapacity basis, sewage collection, invert levels, treated water tank, dual plumbing, overflow
ElectricalConnected load, DG backup, MCC or PLC panel, cabling, earthing, lighting
Mechanical / HVACOdour exhaust for enclosed STPs, fresh air for blower rooms, gas detection
Civil / structuralTank structure, waterproofing, slab loads, access hatches, sleeves
ArchitectLocation, access route, screening and buffer from living spaces
LandscapeIrrigation demand that uses the treated water

Swipe the table sideways to see all columns.

Where does the STP sit in MEP and plumbing design?

The STP sits at the end of the sewage drainage line and at the start of the recycled water line. Sewage flows by gravity from toilets, kitchens and bathrooms through soil and waste stacks into the STP inlet chamber. After treatment, the water moves to a treated water tank. From there, a separate pipe network carries it to flushing cisterns, irrigation or cooling towers.

A typical building STP follows five stages. Tap each stage to see what it does.

Stage 1: Screening

A bar screen at the inlet removes plastics, rags and grit before they reach pumps and the biological tank.

When should the STP enter the design timeline?

The STP should enter at the concept stage, not at good-for-construction (GFC) drawings. Once structural drawings freeze, basement levels and slab depths decide where sewage can flow by gravity. Therefore, a late STP usually means extra lift pumps, a cramped room or a costly redesign. Tap a stage to see the STP decision it needs.

Concept stage

Confirm occupancy and reuse intent, estimate a rough KLD capacity and mark two or three possible STP locations with gravity inflow and tanker access.

What inputs do you need before sizing an STP?

You need six inputs before anyone sizes an STP: occupancy, water demand norm, reuse plan, sewage character, treated water target and site constraints. If one is missing, the vendor has to guess. Those guesses usually end up as an oversized or undersized plant.

  1. Occupancy and population. Count flats and persons per flat, office heads, hotel beds, hospital beds, staff and visitors. Include phasing.
  2. Water demand norm. Use NBC 2016 Part 9 or local bye-law values for each occupancy type.
  3. Reuse plan. List flushing, landscaping, car washing and cooling tower make-up, and decide where excess treated water goes. See how far STP water can be reused.
  4. Sewage character. Note whether it is domestic only, kitchen heavy (oil and grease), hospital waste or mixed with any process water.
  5. Treated water target. The State Pollution Control Board consent (MPCB in Maharashtra) and the reuse application set this.
  6. Site constraints. Check available area, basement depth, groundwater level, soil, tanker access and noise sensitivity.

Typical water demand by occupancy (NBC 2016 Part 9)

OccupancyTotal water demandOf which flushing
Residences with full flushing135 litres per head per dayabout 45
Offices (with canteen)45 litres per head per day20
Factories with bathrooms (with canteen)45 litres per head per day15
Day schools45 litres per head per day20
Hostels and boarding schools135 litres per head per day45
Hotels up to 3 star180 litres per bed per day60
Hotels 4 star and above320 litres per bed per day60
Hospitals up to 100 beds340 litres per bed per day110
Hospitals above 100 beds450 litres per bed per day150

Values are for reference. Always check your city’s bye-laws and the client’s brief, which may set higher figures.

How do you calculate STP size?

You calculate STP size in four steps. First, multiply population by water demand. Next, take about 80% of that as sewage. Then add a design margin, and finally apply a peak factor to size equalisation and pumps. The answer comes out in KLD (kilolitres per day).

STP capacity (KLD) = Population × Water demand (lpcd) × 0.8 ÷ 1,000 × (1 + design margin)
Peak hourly flow (m³/h) = Average sewage flow (KLD) ÷ 24 × Peak factor

Worked example: a 200-flat residential tower

Take a 200-flat tower with 5 persons per flat. Teams commonly assume 4 to 5 persons per flat, so confirm the figure your approving authority accepts.

How to calculate STP size: worked example Population of 1,000 times 135 litres per capita per day gives 135 KLD water demand, times 0.8 gives 108 KLD sewage, plus 10 percent margin gives about 120 KLD STP capacity, with a peak factor of 3.0 giving about 13.5 cubic metres per hour peak flow. How to calculate STP size in 4 steps Worked example: 200 flats, 5 persons per flat, residential norm of 135 lpcd STEP 1 . POPULATION 1,000 persons 200 flats x 5 persons STEP 2 . WATER DEMAND 135 KLD water 1,000 x 135 lpcd STEP 3 . SEWAGE (80%) 108 KLD average sewage 135 KLD x 0.8 STEP 4 . ADD MARGIN ~120 KLD STP capacity 108 x 1.10, rounded up Then check the peak: size equalisation and pumps for it Peak hourly flow = average flow / 24 x peak factor = 108 / 24 x 3.0 = about 13.5 m³/h CPHEEO peak factor: 3.0 up to 20,000 population, 2.5 for 20,000 to 50,000. Confirm the final basis with your STP vendor and approving authority.
Figure 2. How to calculate STP size in 4 steps, using a 200-flat residential tower.
StepCalculationResult
Population200 flats × 5 persons1,000 persons
Water demand1,000 × 135 lpcd135 KLD
Average sewage135 KLD × 0.8108 KLD
Design margin (10%)108 × 1.10about 119 KLD, round to 120 KLD
Peak hourly flow108 ÷ 24 × 3.0about 13.5 m³/h

So a 120 KLD STP with an equalisation tank sized for the peak is a sound starting point here. However, the final number depends on the vendor’s process design, occupancy assumptions and local approval norms.

STP size calculator for mixed-use projects

Add one row per occupancy. Water demand fills in from NBC 2016 Part 9, and you can edit it. For hotels and hospitals, add staff as a separate office row.

Total population0
Water demand0 KLD
Average sewage0 KLD
Suggested STP capacity0 KLD

Peak hourly flow: 0 m³/h (peak factor 3.0)

Indicative estimate only, rounded up to the nearest 5 KLD. Final sizing depends on the process design, local approval norms and site conditions. Prefer a simpler version? Try our free STP capacity calculator.

Should you size on sewage or on total water demand?

Some consultants size the STP on 100% of water demand as a built-in margin. Others use the 80% return factor and add a separate margin. Either way, write the basis into the design brief, so every vendor quotes on the same number. Otherwise, quotes built on different sizing assumptions cannot be compared fairly.

What is STP in manufacturing?

In a manufacturing plant, the STP treats domestic sewage from toilets, canteens and change rooms, while an ETP (effluent treatment plant) treats process wastewater. The two streams usually stay separate. That is because chemicals, oil or heavy metals in process effluent can upset the biology of a sewage plant.

For a factory campus, the consultant typically sizes the STP on the NBC norm of 45 litres per head per day for factories with bathrooms, which includes the canteen. Treated water can then go to gardening, flushing or, after polishing, cooling tower make-up. Note that in pharma quality teams, “STP” can also mean Standard Test Procedure, which is a lab document and not a treatment plant.

What is STP in manufacturing: STP and ETP streams in a factory In a factory, domestic sewage from toilets, canteen and change rooms goes to the STP, while process wastewater from production goes to the ETP. The two streams are kept separate. STP vs ETP in a manufacturing plant Two wastewater streams, two treatment plants. Keep them separate. Factory campus DOMESTIC SEWAGE Toilets, canteen, change rooms, showers STP Biological treatment REUSE Gardening, flushing, cooling tower make-up (after polishing) PROCESS EFFLUENT Washing, rinsing, process water from production ETP Physico-chemical + bio REUSE OR DISCHARGE As per consent conditions, ZLD where mandated Why separate? Chemicals, oil or heavy metals in process effluent can upset the biology of a sewage plant.
Figure 3. STP vs ETP in a manufacturing plant: domestic sewage and process effluent need separate treatment.
FactorSTPETP
TreatsDomestic sewage from toilets, canteen and bathroomsProcess effluent from production
Main pollutantsOrganic load (BOD), suspended solids, pathogensChemicals, oil, colour, metals, high COD (varies by industry)
Main processBiological (MBBR, SBR, ASP and others)Physico-chemical plus biological, tailored to the effluent
Design basisHeadcount × water demandProduction process and effluent analysis
Typical reuseFlushing, gardening, cooling tower after polishingDepends on treatment level; ZLD where mandated

Swipe the table sideways to see all columns.

Where should the STP go? Space and installation choices

The best STP location is the lowest practical point that sewage reaches by gravity, with road access for sludge tankers and distance from living spaces. Four layouts cover most projects.

STP installation options: underground, basement, above ground and containerised Four common STP installation layouts in buildings, each shown as a simple cross-section with its best use. Where can the STP go? 4 common layouts STP Underground Below open ground or driveway, gravity inflow STP Basement / podium Dense towers, needs exhaust and headroom planning STP Above ground Industrial campuses, easy access, may need lift pumps PACKAGED STP Containerised / terrace Small or phased capacity, tight or retrofit sites
Figure 4. Four common STP installation layouts in buildings.
LayoutBest forWatch out for
Underground (below open ground or driveway)Plots with open area and gravity inflowGroundwater, waterproofing, traffic loads on covers
Basement or below podiumDense urban towers with no open groundExhaust, headroom, flooding risk, confined space safety
Above groundIndustrial campuses and plots with spaceLift pumps for deep inflow, screening, noise
Containerised or terraceSmall, phased or retrofit projectsCapacity limits, structural load, future expansion

Swipe the table sideways to see all columns.

Technology choice changes the footprint more than most teams expect. For example, compact attached-growth processes such as MBBR need less tank volume than conventional activated sludge. Brivith’s patented BIO-DRUM MBBR needs 50 to 60% less space than conventional STPs, depending on site conditions.

How should the STP coordinate with civil and electrical design?

Coordinate the STP with civil and electrical teams before structural drawings freeze, because tank depths, slab loads and power provisions are expensive to change later. Use the tabs below as a meeting agenda.

STP coordination map for MEP, civil and electrical teams The STP sits at the centre of six disciplines: plumbing, electrical, ventilation, civil and structural, architecture and landscape, each with its key coordination inputs. Who coordinates what on an STP Six disciplines touch the STP. Agree each interface before structural drawings freeze. STP in MEP Plumbing / PHE Capacity basis, inverts, lift pumps, treated water tank, dual plumbing Electrical Connected load, DG backup, MCC/PLC panel, cabling, earthing Ventilation / HVAC Odour exhaust, gas detection, blower room fresh air Civil & structural Tank depths, waterproofing, slab loads, hatches, sleeves Architect Location, access route, screening, buffer from living spaces Landscape Irrigation demand matched to treated water output
Figure 5. Who coordinates what on an STP in MEP design.
  • Match tank invert levels to incoming sewer inverts.
  • Check tank depths against groundwater and raft levels.
  • Specify waterproofing and leak testing for every wet tank.
  • Share equipment and water loads for slab and beam design.
  • Provide hatches, ladders and access for each chamber.
  • Plan sludge tanker access within suction hose reach.
  • Place sleeves and puddle flanges for every pipe entry.

What are the most common STP design mistakes?

The costliest STP mistakes happen on paper, long before the plant starts. Here are eight that consultants see again and again. Tap a card to see the fix.

Which STP technology should a consultant specify?

Specify the technology on space, power cost, operator skill and treated water quality, not on capital cost alone. The table below gives a quick view, and our MBBR vs SBR vs ASP comparison covers each option in detail.

TechnologyFootprintBest fit
ASP (activated sludge)LargestLarge plants with space and skilled operators
SBR (sequencing batch reactor)MediumSites that need tight control and have good automation
MBBR (moving bed biofilm reactor)CompactResidential and commercial buildings with load swings
BIO-DRUM MBBR (Brivith, patented)Compact, 50 to 60% less space than conventional*Space-tight towers that prioritise low power and odour control

*Performance figures depend on site conditions. BIO-DRUM MBBR is Brivith Engineering’s own patented technology.

STP design checklist for MEP consultants

Use this 12-point checklist before you issue the STP brief. Tick items as you close them.

0 of 12 done
Brief ready. Send it to Brivith for a free technical review: WhatsApp us or email sales@brivith.com.

Summary: STP in MEP at a glance

  • An STP in MEP is the end of the drainage system and the start of the recycled water system.
  • Size it from population × water demand × about 0.8, then add a stated margin and check the peak.
  • Fix its location, levels and power at the concept and schematic stages.
  • Coordinate civil, electrical, ventilation and dual plumbing before structural drawings freeze.
  • Choose the technology on lifecycle cost, space and operator skill, not capital cost alone.

Frequently asked questions

What is STP in MEP?

An STP in MEP is the sewage treatment plant designed within a building’s plumbing and public health scope. The MEP consultant sets its capacity, location, levels and reuse plan, while electrical and mechanical teams provide power and ventilation. The STP vendor then designs the treatment process and equipment.

How do you calculate STP size for a building?

Multiply the population by the water demand per head, such as 135 lpcd for residences, and take about 80% as sewage. Then add a design margin. For 1,000 residents, 1,000 × 135 × 0.8 gives 108 KLD, or about 120 KLD with a 10% margin. Finally, apply a peak factor to size the equalisation tank. Try the free STP capacity calculator.

What is STP in manufacturing?

In manufacturing, an STP treats domestic sewage from toilets, canteens and change rooms on a factory campus. Process wastewater goes to a separate ETP, because chemicals and oils can upset the biology of a sewage plant. In pharma quality teams, STP can also mean Standard Test Procedure.

Is an STP mandatory for buildings in India?

Large building projects generally need one. Projects above 20,000 m² built-up area usually require prior Environmental Clearance under the EIA Notification 2006, and an STP is a standard condition. Local bye-laws and pollution control boards may also require STPs for smaller projects, so check current norms for your city. Read: is an STP mandatory for housing societies in Pune?.

How much space does an STP need?

Space depends on capacity, technology and layout. Compact MBBR plants need less tank volume than conventional activated sludge plants. Brivith’s BIO-DRUM MBBR needs 50 to 60% less space than conventional STPs, depending on site conditions. Share your capacity and site plan for an accurate space estimate. Compare STP technologies: MBBR vs SBR vs ASP.

Who designs the STP: the MEP consultant or the STP vendor?

Both play a part. The MEP consultant sets the capacity basis, location, levels, interfaces and reuse plan. The STP vendor designs the process, equipment and controls and gives the performance guarantee. A clear interface list between the two avoids gaps on site.

Read the guide. Consultants: DM us for technical details for your next project.

Share your occupancy, site plan and reuse plan, and Brivith’s engineers will suggest an STP capacity, layout and technology for your project.

BE

Written by the Brivith Engineering team. Brivith Engineering LLP, Hadapsar, Pune, designs and builds sewage treatment plants from 5 KLD to 5,000 KLD, including the patented BIO-DRUM MBBR. The company is led by founder Vikram Nigade, who brings 25+ years of engineering experience. Questions about whether your project needs an STP? Read is an STP mandatory for housing societies in Pune.

Sources

  1. CPHEEO Manual on Sewerage and Sewage Treatment Systems, Ministry of Housing and Urban Affairs (80% sewage return, design guidance)
  2. CPHEEO peak factor by contributory population, NCR Planning Board repository
  3. National Building Code of India 2016, Part 9 Plumbing Services, Bureau of Indian Standards (water demand by occupancy)
  4. Supreme Court on Environmental Clearance for building projects above 20,000 m², Khaitan & Co via Mondaq, September 2025